Analyses the rules of Directive 2014/24 art.73 on the termination of a public contract due to its "substantial" modification which would have required a new procurement procedure pursuant to art.72, including a comparison of how art.73 has been implemented in the UK and the Scandinavian states. Identifies specific issues regarding art.73 that have been left to the discretion of Member States and comments on the scope for uncertainty this creates.
Alkuperäiskieli | englanti |
---|---|
Sivut | 187-199 |
Julkaisu | Public Procurement Law Review |
Numero | 4 |
Tila | Julkaistu - kesäk. 2017 |
OKM-julkaisutyyppi | A1 Vertaisarvioitu alkuperäisartikkeli |
Tapahtuma | Global Revolution VIII: Public Procurement - Nottingham, Iso-Britannia Kesto: 12 kesäk. 2017 → 13 kesäk. 2017 http://nottingham.ac.uk/conference/fac-socsci/pprg-global-revolution-conference-vii/index.aspx |
Tieteenala
- Oikeustiede
Aktiviteetit
- 1 Konferenssiesitelmä
-
Termination of public contract following substantial modification
Halonen, K.-M. (Puhuja)
13 kesäk. 2017Aktiviteetti: Esitelmä › Konferenssiesitelmä